STATUS
GREEN
REALITY
PENDING VERIFICATIONAMBER · BUFFER 3 OF 9 DAYS

Green is where the lying happens.

Every project has three versions: the plan, the one described in meetings, and the one actually happening. Red, Amber, Liar is a field guide to the distance between them, plus a club of PMs who close it.

The Club app · Honest RAG check

The colour is computed. Not negotiated.

Status comes from evidence: buffer left, decisions waiting, dependencies with no date. To call it Green anyway, you write down why.

Moon and Back · Week 8Concept

Honest RAG check

Reported statusGREEN
Evidence statusCHECKING…

Buffer 9 of 9 days left

Not just a book

A field kit for the job nobody sees.

Every tool traces back to a chapter. No Earned Value formulas. Just the instincts nobody warned you about.

The Project Zoo · Ch 8

24characters

You deal with them 24 hours a day.

Name the pattern, never the person.

Estimate ladder

“Maybe, assuming” survives all the way to the slide.

Ch 13
Rough±40%
Working±20%
Targetaim
Commitmentfact

Leave radar

Ask a week early. Not two days late.

Moon and Back

Three case files. Green, then Amber, then Red.

WK 0 ········· WK 8 ········· GO-LIVE

Decision log

12 days

“A decision that has been sitting unanswered for twelve days is called ‘under discussion.’”

Try This Monday

Weekly

“Find one date in your plan that began life as ‘roughly.’”

From the Zoo

Recognise anyone?

Meet all 24 →

Field Notes · every Monday

What is actually happening?

All notes →

Reels & videos

Thirty-second doses.

Instagram · soonYouTube · soon

Status translator

What did they actually mean?

None of these phrases are necessarily lies. That is what makes them dangerous.

Reported

Pick a phrase. Reality will be along shortly.